The disclosure was made by the Minister of Finance and Economic Planning, Yusuf Murangwa, on June 12, 2025, during a press briefing following his presentation of the draft budget and medium-term economic strategy to a joint session of Parliament.
Minister Murangwa noted that one of the major priorities in the upcoming fiscal year is to advance the full-scale construction of the new international airport.
'We previously carried out feasibility studies and completed preliminary works over a significant period. However, we now have a firm commitment to complete the airport by 2028. This fiscal year marks the beginning of full implementation,' he stated.
Regarding the funding, he explained, 'So far, we've planned for $600 million. As you know, we have strategic partners, including Qatar. While this amount is part of the budget plan, the actual implementation phase will give us a clearer financial outlook.'
Murangwa confirmed that construction of the airport is scheduled to be completed by 2028 and will have the capacity to serve up to seven million passengers annually.
While addressing Parliament, the minister said current progress on the project stands at approximately 25% to 30%. Work on the runways, access roads, and water systems has been completed, and the project has now entered the building phaseâ"expected to employ more than 6,000 workers.
In 2019, Qatar Airways partnered with the Government of Rwanda, securing a 60% stake in the airport project, which was then estimated to cost more than $1.3 billion.